New construction · Single-family
9 Avery Street new construction
The original 1950 bungalow was replaced with a new two-story, 3-bedroom, 3-bath home with about 1,547 sq ft of finished living space.
- Location9 Avery Street, Meredith, NH
- Year2023–2026
- TypeNew construction · Single-family
- Property9 Avery Street, Meredith, NH
Scope
- Planning and permitting (permit set dated December 2023)
- Demolition of the original 820 sq ft bungalow, February 2024
- New foundation, with insulated concrete form (ICF) walls
- Two-story framing, roof, siding, trim and a street-facing balcony
- Full interior finishes, furnishings and a sunroom
- Site walls, paved driveway, entry walkway and back patio, fall 2026
Timeline
- April 2023 — The original bungalow, before work began
- February 2024 — Demolition; lot cleared
- October 2024 — Foundation walls in place
- January 2025 — ICF walls go up
- March 2025 — Two-story framing
- December 2025 — Siding, trim and balcony
- June 2026 — Deck and balcony complete
- September 2026 — Interiors finished and furnished
- October 2026 — Site walls, driveway, walkway and patio